Phase 2 Bond Schedule
FWPS will have a robust process to incorporate stakeholder voice including our students, staff, parents, and community. This includes community forums to share and receive comments throughout the design process. Also, the community will be informed of progress updates throughout each school's construction.
The district has developed a preliminary project schedule for the 2017 bond that is subject to change. The schedule is structured in a way to maintain current tax levels.
The initial projects include four elementary schools, Evergreen Middle School and Thomas Jefferson High School. As a high school is the most costly to build, it is placed earlier in the timeline in an effort to mitigate inflation.
Lake Grove Elementary
The planning and design phases began 2018 and concluded in spring 2019. Construction began in 2019, and scholars are scheduled to occupy the building in Winter 2020.
Mirror Lake Elementary
The planning and design phases began 2018 and concluded in spring 2019. Construction began in 2019, and scholars are scheduled to occupy the building in Winter 2020.
Wildwood Elementary
The planning and design phases began 2018 and concluded in spring 2019. Construction began in 2019, and scholars are scheduled to occupy the building in Winter 2020.
Star Lake Elementary
The planning and design phases began in 2018. Construction is scheduled to begin in 2020, and scholars are scheduled to occupy the building in the fall of 2022.
Evergreen Middle
The planning and design phases began in 2018. Construction is scheduled to begin in 2020, and scholars are scheduled to occupy the building in the winter of 2021.
Thomas Jefferson High
The planning and design phases began in 2018. Construction is scheduled to begin in winter 2020, and scholars are scheduled to occupy the building in the fall of 2021.
Olympic View K-8
The planning and design phases are scheduled to begin in 2020. Construction is scheduled to begin in 2022, and scholars are scheduled to occupy the building in the fall of 2023.
Illahee Middle
The planning and design phases is scheduled to begin in 2022. Construction is scheduled to begin in 2024, and scholars are scheduled to occupy the building after winter break, January 2025.
Memorial Stadium
The planning and design phases is scheduled to begin in 2024. Work is scheduled to begin in 2025, and work is scheduled to be completed in the fall of 2025.
Misc. Projects
Safety enhancements at all sites and major maintenance needs at selected sites will begin in 2018 and continue through 2022.